We were contacted by a facilities manager for a bank in South Jersey about an issue they were having with their underground tube system for the drive up teller. Water kept getting into the system and creating problems. After months of collaboration between ourselves, the bank and an architect a design was drawn for an overhead structure for the drive up.
We needed to install concrete pier footings for each steel post. The steel posts were 18’ high and the system was 110’ long. After the steel was installed a specialized VAT contractor installed the tube system and the electric. We then frame a box type structure with a roof around the tubing to keep as much water away as possible and then roofed it with a special product called TPO and used a CertainTeed board and batten siding.
It was an unusual project with a custom design. We’ve been helping our customers resolve diffiecult issues for 25 years and we can help you too.